Gas generator payback: case studies from our sites

Abstract yield percentages say little. Instead, here are sites we built and service: what was installed, what a kWh ended up costing against the grid, how long the payback took and what drives it.

Two Weichai 400 kW gas gensets in the engine room of a plastics plant, Yaroslavl region
Economics
Topic
6 min
Reading time
Nov 3, 2026
Published in English
Key points
  • Yaroslavl region: own kWh at 3.6 RUB/kWh instead of 7.1 RUB/kWh from the grid, 19.35 million RUB saved per year, payback in about 13 months.
  • Vologda region: the same 640 kW on two Weichai 400 kW units for a manufacturing plant, 35 days of delivery plus 15 days of commissioning.
  • Payback starts at commissioning, not at payment: 35–45 days of delivery plus 15 days of commissioning on these sites.
  • These are results of specific sites, not a forecast for yours and not a public offer.

Two sites of the same size

Both sites run 640 kW of continuous power on two Weichai 400 kW gas generator sets, both commissioned in 2025. The tasks were different, and so was the scope.

SiteLoadEquipmentDelivery + commissioning
Vologda region, manufacturing640 kW continuous2 × Weichai 400 kW35 + 15 days
Yaroslavl region, plastics plant640 kW, around the clock2 × Weichai 400 kW, DEIF AGS 150 Extended controller45 + 15 days

The numbers from Yaroslavl

CapEx incl. VATOwn kWh costGrid kWh costSavings per yearPayback
21,000,000 RUB3.6 RUB/kWh7.1 RUB/kWh19,353,600 RUB≈ 13 months
32,800 RUBper kW of continuous power, Yaroslavl, turnkey
3.5 RUBsaved on every kWh in Yaroslavl
19.35 million RUBsaved per year at 640 kW around the clock

The plant runs around the clock: injection molding machines, dryers, compressors, a flat load that never switches off. It runs on own gas power, with the grid kept as a backup. A kWh of its own generation costs 3.6 RUB including gas and service, against 7.1 RUB from the grid. The difference is 19,353,600 RUB a year, which paid back the 21,000,000 RUB project in about 13 months. The scope included a DEIF AGS 150 Extended controller that synchronizes the two units, shares the load and takes one unit out for maintenance without stopping the shop. The equipment was financed through a Russian leasing company.

In the Vologda region the task was to cut the electricity bill of a manufacturing plant with the same two-unit layout. We show this site for its scope and timing; its financial figures are not published here.

Engine room building of the gas power plant at a plastics factory, Yaroslavl region, with the gas line and gas pressure regulating cabinet
Yaroslavl region: the engine room built for two 400 kW units, with its own gas line and pressure regulating cabinet.

A third site in Samara shows how scope changes the comparison. There, three Weichai units on open frames (1.2 MW rated, 960 kW continuous) stand in a purpose-built building with sound insulation instead of canopies. Its budget includes the building, so it cannot be compared with the Yaroslavl plant on CapEx alone. We do not publish its financial figures. See the Samara case study.

Comparing sites by CapEx makes no sense if one figure is a genset alone and another is a genset, a building and everything around it.

What drives the payback period

  1. Your current tariff. The more you pay the grid, the faster your own generation pays back.
  2. Your gas price. The other half of the equation. See what a kWh of own gas generation costs.
  3. Load. A genset running around the clock pays back twice as fast as one running a single shift.
  4. What exactly you buy. One genset, or a complete plant with a building, a container or mining equipment.

Commissioning time

Payback starts at commissioning, not at payment. In the Vologda region delivery took 35 days plus 15 days of commissioning; in the Yaroslavl region 45 and 15. Our flagship 15 MW site in the Saratov region was commissioned in 75 days. See the 15 MW case study.

All figures come from sites FastMine built. Your result will differ: it depends on your gas price, current tariff and operating mode. This is an estimate based on completed projects, not a guarantee of savings and not a public offer. Send us your bills and gas data, and we will calculate your case.
Own gas power for your plantSend your monthly consumption and current tariff. We will calculate the plant, gas consumption, CapEx and expected payback for your site.Gas power for industry

Frequently asked questions

How long does a gas generator take to pay back?

On our Yaroslavl site, about 13 months: own kWh at 3.6 RUB/kWh against 7.1 RUB/kWh from the grid, with a load around the clock. The period depends on your grid tariff, gas price and load. This is the result of a specific site, not a forecast or a guarantee.

What does a 640 kW gas power plant cost turnkey?

21,000,000 RUB incl. VAT in the Yaroslavl region, where the scope included a DEIF controller that runs the two units in parallel. The budget for your site depends on the building or enclosure, the gas connection and the controls.

How long does it take to commission a gas genset?

On these sites: 35–45 days of delivery plus 15 days of commissioning. Our 15 MW site in the Saratov region took 75 days from the start of work.

Read next

This article is an English adaptation of our Russian original (Jul 29, 2026), rewritten for international readers. Prices are in RUB incl. VAT for supply in Russia; USD amounts are for reference only. Contracts are signed with TDM LLC (INN 9726051386) under Russian law, in RUB. Figures are estimates, not a public offer or a guarantee of income.