Surovskoe: 8 MW, our first site on own gas generation
The site where FastMine started mining on its own generation. 8 MW of gas generator sets right on site: natural gas goes into the gensets and the electricity goes straight into mining, with no grid in between. The know-how gained here is what we later used to build our energy centers, including the 15 MW flagship.

How the site developed
Containerized gas gensets stand right at the site. Gas goes to the units directly and electricity goes straight into mining, bypassing the grid and the grid connection process.
The site grew in phases: gensets and hosting modules were added as capacity came online. We learned to scale a running site without stopping working equipment.
This is where we built genset maintenance by operating hours, lubricant selection for continuous gas operation, the spare parts supply chain and our own monitoring of generation and miners.
The solutions developed here became the basis for how we build energy centers. The 15 MW flagship reached design capacity in 75 days because nothing had to be designed or debugged from scratch.
How the site is run
- Containerized gensets: weather protection and noise reduction without capital construction
- Genset maintenance by operating hours, done by our own operations team
- A consumables supply chain developed here and then moved to the flagship site
Photos from the site












Not yet published: the exact genset fleet and the number of ASICs hosted at this site.
Questions
How is Surovskoe different from the 15 MW energy center?
In order and role. Surovskoe is the first site where we started mining on our own generation and grew to 8 MW. Rybushanskoe was built on that experience and therefore reached 15 MW in 75 days. Both sites are in operation.
Why does the experience of a first site matter to a client?
Because energy centers go wrong in operation rather than in design: oil selection for the specific gas, maintenance intervals, spare parts supply, collecting telemetry from mixed equipment. This cannot be calculated in advance, only accumulated. We went through it with our own money on our own site, not on a client's.
Why put generation right at the site?
It removes the main middleman, the grid. Gas goes to the units directly and the electricity goes straight into mining. No grid connection or capacity approvals are needed, and the cost per kWh is set by the cost of generation, not by a utility.
Other projects




Related
Talk to the team
We answer in English. Tell us what you are looking for (hosting, equipment or an investment) and we will come back with numbers, documents and, if you wish, a video tour or a site visit.